Street Opening Permits are required for excavations or other work in a city street that disturbs the street surface.
Outlined below are the basic application procedures for Street Opening Permits. These are in addition to the "Common Requirements" listed at the beginning of this section. Additional requirements are contained in...
Building Operations/Construction Activity Permits apply to construction activities that take place within the street and are generally associated with construction work adjacent to the street. A valid permit issued by DOB is usually required in order to apply for permits in this category. Some of the activities covered include...
Certain circumstances are considered to be emergencies, meaning situations that endanger the public safety or cause or are likely to cause the imminent interruption of service. Special and separate procedures govern emergency work: one for utility access covers (including those for "manholes," valve covers and grates) and one...
This section describes the application and review process for obtaining approvals to construct or repair vaults under the sidewalks of New York City streets. NYC DOT issues permits for two types of vaults: building vaults and transformer vaults.
A building vault, as described in Section 2-13 of the Highway Rules, is any...
PEU performs the initial review of all applications for building vault permits and licenses. A DOB-approved plan must be obtained and submitted to PEU with the application for a final approval and permit. Different from DOB, DOT plans requires 600 PSF live loads on all sidewalk doors, gratings, covers and vault structures.
If...